Construction work at Eagles Meadow is well under way, the steelworks has now been erected and retailers fit out of units will commence in Spring 2008.

  • Development Construction Progress July 2006

    Development Construction Progress July 2006

  • Development Construction Progress October 2006

    Development Construction Progress October 2006

  • Development Construction Progress January 2007

    Development Construction Progress January 2007

  • Construction Progress February 2007

    Development Construction Progress February 2007

  • Development Construction Progress April 2007

    Development Construction Progress April 2007

  • Development Construction Progress May 2007

    Development Construction Progress May 2007

  • Development Construction Progress Update July 2007

    Development Construction Progress Update July 2007

  • Development Construction Progress September 2007

    Development Construction Progress September 2007

  • Development Construction Progress October 2007

    Development Construction Progress October 2007

  • Development Construction Progress December 2007

    Development Construction Progress December 2007

  • Development Construction Progress January 2008

    Development Construction Progress January 2008

  • Development Construction Progress April 2008

    Development Construction
    Progress April 2008

  • Development Construction Progress June 2008

    Development Construction
    Progress June 2008

  • Development Construction Progress August 2008

    Development Construction Progress August 2008

Programme of Work

May 2006 – Construction work commenced
October 2006 – First steelwork erected
February 2007 – 2nd floor beams are erected
March 2007 – The new link road opens with the existing flyover demolished in June 2007
Spring 2008 – Fit out for occupiers will commence
October 2008 – Eagles Meadow opens to the public